Close Menu
  • Home
  • Maritime
  • Offshore
  • Port
  • Oil & Gas
  • Energy
  • Technology
  • Incidents
  • Environment
  • Events
    • Maritime
    • Offshore
    • Oil & Gas
    • Energy
  • Advertising
  • Contact
Facebook X (Twitter) Instagram LinkedIn
Trending
  • Teledyne Valeport Water Announces Shallow Water Hyperion32
  • Second Bulker Refloated After Grounding off Sweden
  • bound4blue WAPS calculation method wins DNV nod of approval
  • NOAA: Operational Forecast System Informs Shipwreck Oil Spill Scenarios
  • Tourist boat carrying 89 passengers capsizes in Bali
  • Lithuania to relaunch 700MW offshore wind tender next week
  • UML ready to welcome first newbuild tanker fitted with WAPS
  • Mother Ship with USV Flotilla Could Boost Coast Guard Capabilities
Facebook X (Twitter) Instagram LinkedIn
Maritime247.comMaritime247.com
  • Home
  • Maritime
  • Offshore
  • Port
  • Oil & Gas
  • Energy
  • Tech
  • Incidents
  • Environment
  • Events
    • Maritime
    • Oil & Gas
    • Offshore
    • Energy
  • Advertising
Maritime247.comMaritime247.com
Home»Energy»Jaxport nears halfway mark in $60M berth enhancement project
Energy

Jaxport nears halfway mark in $60M berth enhancement project

February 15, 2025
Facebook Twitter LinkedIn WhatsApp Reddit Tumblr Email
Share
Facebook Twitter LinkedIn Email

Expansion Project at Jacksonville Port Authority Wraps Up

Contractors for Florida’s largest container port Jacksonville Port Authority (Jaxport) have completed a year-long, multi-million dollar construction project to expand Vehicle Berth 22 at the Blount Island Marine Terminal.

According to Jaxport, this expansion is part of a $60 million initiative aimed at enhancing efficiencies and enabling the berth to accommodate larger vehicle vessels than before. The Florida Department of Transportation covered 75% of the funds, with Jaxport matching the remaining 25%.

The completion of Berth 22 now allows ships with an overall length of approximately 750 feet (228.6 meters) to dock at the terminal.

Construction has already begun on the second berth at Blount Island, with an estimated completion time of 24 months, set for early 2027.

“Maintaining congestion-free vessel facilities as cargo volumes grow is an important part of our short and long-term planning processes. These upgrades allow us to serve our auto customers more efficiently while providing additional capacity for future growth, so we can continue to build on our position as one of the nation’s top vehicle-handling ports,” said Jaxport CEO Eric Green.

Investments in Port Infrastructure

In recent years, Jaxport has made significant investments to improve its berths and operational efficiency at the Blount Island container terminal. The final stage of a $100 million berth enhancement project at the SSA Jacksonville Container Terminal (JCT) was completed in spring 2022, with support from the Florida Department of Transportation.

Additionally, over $72 million in phased yard improvements to accommodate 500,000 TEUs annually at SSA JCT were initiated, funded by SSA Atlantic and a $20 million grant from the US Department of Transportation Maritime Administration (MARAD).

See also  Aker Solutions secures work on German offshore wind project

Jaxport also secured a $23.5 million grant from the Department of Transportation in November 2022 to reduce harmful pollutant emissions. Another $31.2 million was allocated for purchasing environmentally friendly cargo handling equipment for SSA JCT.

Industry-wide Decarbonization Efforts

As the maritime industry focuses on decarbonization efforts, ports across the US are investing in eco-friendly equipment, technology, and infrastructure. In November 2024, MARAD allocated nearly $580 million from the Bipartisan Infrastructure Law to fund 31 port improvement projects in 15 states and one US territory.

Furthermore, the US Environmental Protection Agency (EPA) recently announced the recipients of the Clean Ports program grant, aimed at supporting the deployment of zero-emission equipment and technology.

60M Berth enhancement Halfway Jaxport Mark nears project
Share. Facebook Twitter LinkedIn Tumblr Telegram Email

Related Posts

bound4blue WAPS calculation method wins DNV nod of approval

June 8, 2025

UML ready to welcome first newbuild tanker fitted with WAPS

June 8, 2025

BAR Technologies, Brevik Engineering present wind-assisted LCO2 carrier design

June 7, 2025
Top Posts

Duties of Bosun (Boatswain) on a Ship

February 1, 2025

Top 10 Biggest RORO Ships In The World

February 15, 2025

Sea-Doo Switch recall underway after serious safety concerns

March 2, 2025

CMA CGM settles US sexual harassment case

January 11, 2025
Don't Miss
Knowledge

Case of a Mutual Fund Advisor/Distributor

February 7, 2025

Like all financial products, Mutual Funds too have an intermediary who connects an investor to…

Noble rig scores multi-well drilling gig offshore Suriname

January 1, 2025

Tokyo Attracts Industry Leaders for Japan Energy Summit 2025

March 12, 2025

SBM Offshore’s NearZero FPSO design gets ABS’ blessing

May 7, 2025

Subscribe to Updates

Your Weekly Dive into Maritime & Energy News.

About Us
About Us

Stay informed with the latest in maritime, offshore, oil & gas, and energy industries. Explore news, trends, and insights shaping the global energy landscape.

For advertising inquiries, contact us at
info@maritime247.com.

Facebook X (Twitter) YouTube LinkedIn
Our Picks

Fredriksen’s SFL wins $48m in Seadrill rig dispute case

February 8, 2025

Is The Black Rock, CK Hutchison Port Deal In Peril?

March 16, 2025

General Dynamics Secures $12 Billion U.S Navy Contract For 2 More Virginia-Class Submarines

May 3, 2025

Subscribe to Updates

Your Weekly Dive into Maritime & Energy News.

© 2025 maritime247.com - All rights reserved.
  • Contact
  • Privacy Policy
  • Terms & Conditions
  • Advertising

Type above and press Enter to search. Press Esc to cancel.