Close Menu
  • Home
  • Maritime
  • Offshore
  • Port
  • Oil & Gas
  • Energy
  • Technology
  • Incidents
  • Environment
  • Events
    • Maritime
    • Offshore
    • Oil & Gas
    • Energy
  • Advertising
  • Contact
Facebook X (Twitter) Instagram LinkedIn
Trending
  • HD Hyundai, H-Line Shipping to develop AI-powered autonomous ship technology
  • Panama’s Comptroller Asks Court to Void Hutchison’s Terminal Concession
  • New 500 kV submarine cable contract to keep ZTT busy offshore China
  • India commissions 1 MW green hydrogen plant at Kandla Port
  • BP renews EnerMech’s contract for work across Caribbean platforms
  • Nexans, Crowley Wind Services to Build Cable Lay Barge for US Ops
  • How marine service providers are helping shipping meet its sustainability goals
  • Garmin Q2 results show growth in all business segments
Facebook X (Twitter) Instagram LinkedIn
Maritime247.comMaritime247.com
  • Home
  • Maritime
  • Offshore
  • Port
  • Oil & Gas
  • Energy
  • Tech
  • Incidents
  • Environment
  • Events
    • Maritime
    • Oil & Gas
    • Offshore
    • Energy
  • Advertising
Maritime247.comMaritime247.com
Home»Energy»Project ONE: Giant plant modules arrive in Antwerp on board COSCO ship
Energy

Project ONE: Giant plant modules arrive in Antwerp on board COSCO ship

January 19, 2025
Facebook Twitter LinkedIn WhatsApp Reddit Tumblr Email
Share
Facebook Twitter LinkedIn Email

The Arrival of First Furnaces at Port of Antwerp-Bruges Marks a Milestone for European Chemical Sector

On January 15, 2025, COSCO Shipping’s heavy lift vessel Zhi Yuan Kou arrived at the Project ONE site in Antwerp with a cargo of first furnaces, representing an important step for the Port of Antwerp-Bruges and the European chemical sector.

The 195.2-meter-long semi-submersible vessel arrived in Antwerp after a long overseas voyage from Thailand.

British multinational conglomerate INEOS—one of the world’s largest chemical producers—received the module containing the first two furnaces destined for Project ONE’s new ethane cracker at the quay of the construction site in Lillo, Antwerp.

Specifically, the furnaces form the heart of the ethane cracker under construction: in the furnace section, ethane is converted to ethylene by bringing the ethane to a high temperature in the presence of steam.

Weighing as much as 6,000 tonnes, more than 32 meters wide and 60 meters high, this is said to be “one of the largest and most spectacular industrial ship transports ever” in the Port of Antwerp-Bruges. The monetary value of the module with 2 furnaces is also considerable: it amounts to as much as €150 million.

“The arrival of the first furnaces for Project ONE marks a crucial milestone for Port of Antwerp-Bruges and the European chemical sector. This project not only strengthens Antwerp’s role as a strategic hub, but also helps anchor a forward-looking and sustainable industry in Europe. This investment is necessary for the European economy and we are therefore proud to see this progress at the port and look forward to the further realization of this pioneering investment,” Jacques Vandermeiren, CEO Port of Antwerp Bruges, commented.

See also  Aker Solutions seals second deal for German offshore wind project

The remaining four furnaces are scheduled to be delivered in the first quarter of this year.

“The arrival of the first furnaces at the Antwerp site after a long overseas journey is a spectacular and joyous moment for everyone involved in the making of our project. It cannot be ignored: Project One is no longer a virtual project on paper, but is increasingly gaining a foothold in the port. It is hugely motivating to see a plant actually rise after all these years of preparation. A lot of work has been done in 2024, but by 2025 the centre of gravity of construction activity will be fully in Antwerp,” John McNally, CEO of INEOS Project ONE, highlighted.

Special Overseas Transport: From Sattahip to Antwerp

The overseas transit of the furnaces, which were manufactured in Thailand, is considered one of the most critical moments during the lifetime of the furnaces, which last around 50 years.

Because of the precarious situation in the Red Sea, the transport had to make a diversion via the Cape of Good Hope and was underway for a total of 55 days over a distance of 12,500 nautical miles.

To keep the cargo stable during overseas transport, it was reinforced with a steel framework and literally welded to the ship. The vessel will stay another couple of days at the quay wall for releasing and unloading the module with furnaces and pipe-racks.

The round-the-clock activity will be carried out by Flemish contractor Sarens, which is also in charge of the Self Propelled Modular Transporter (SPMF) transport and jacking to bring the components to the correct position for installation on site; a huge endeavor due to the enormous dimensions of the plant units.

See also  Iran's "Shadow" Vessel Fleet Hit with Fresh Sanctions

The Modular Concept

Project ONE is also generating a lot of activity outside Antwerp. As many as 10,000 workers worldwide were mobilized for the construction of the new plant.

A large number of these were at work in the module yards in Thailand, Abu Dhabi, and the Philippines, a phase that is now gradually being completed. A total of 10 million man-hours were performed at the Thailand yard.

Modules like furnaces require specialized expertise both for their production and assembly. There are only a limited number of construction yards around the world that are adequately equipped and accessible to ocean-going vessels for this purpose.

Moreover, there is too little space at the construction site in Antwerp both for the storage of materials and the construction of these large-scale modules while civil and underground works are in full swing.

For this modular method of construction, INEOS relies on the extensive expertise of its technology partner Technip Energies.

With the arrival of the modules in Antwerp, the plant can be built like Lego bricks connected on-site.

Low-Carbon Furnaces

The INEOS cracker furnaces are equipped with ultra-low NOx burners and combustion air preheaters that ensure maximum reduction of NOx emissions and maximum energy efficiency. Because of the unique combination of features, the furnaces selected for Project ONE have ‘the lowest’ carbon footprint compared to all other similar alternatives, as per INEOS.

They are suitable for using fuel with a high hydrogen content. From the first day the ethane cracker is operational, INEOS will already be able to meet 60% of its heat demand with low-carbon hydrogen instead of natural gas.

See also  KEYS Azalea Completes Japan's First LNG Bunkering Op for Cruise Ship

Advanced technology, coupled with the reduced use of natural gas means the Project One cracker will have ½ the carbon footprint per tonne of product compared to the next best cracker in Europe. And the technology is already poised to switch to 100% hydrogen as soon as sufficient volumes of affordable climate-friendly hydrogen become available.

The Project

Project ONE is an investment by INEOS in the Antwerp chemical sector for the construction of an ethane cracker. The investment amounts to over four billion euros, making it the largest investment in European chemistry in more than 20 years.

The ethane cracker will provide the heat needed to convert ethane into ethylene, one of the most important building blocks in the chemical industry.

Ethylene is a fundamental raw material used in numerous applications such as sustainable energy solutions. It is also used in lightweight parts for cars and wind turbines, insulation materials for the construction industry, or pipes for transporting drinking water.

The end of 2026 is targeted as the start of operation. The foundation stone was laid on December 15, 2022.

Antwerp arrive Board COSCO Giant modules plant project Ship
Share. Facebook Twitter LinkedIn Tumblr Telegram Email

Related Posts

HD Hyundai, H-Line Shipping to develop AI-powered autonomous ship technology

July 31, 2025

India commissions 1 MW green hydrogen plant at Kandla Port

July 31, 2025

1 MWp floating solar project underway in Paraguay

July 31, 2025
Top Posts

Duties of Bosun (Boatswain) on a Ship

February 1, 2025

China Fights Australia’s Plans to Reclaim Darwin Port Citing U.S. Influence

May 27, 2025

Fire-Stricken Wan Hai 503 Continues to Drift Off Indian Coast as Salvage Efforts Intensify

June 11, 2025

Car Carrier ‘Morning Midas’ Catches Fire with Electric Vehicles Off Alaska

June 5, 2025
Don't Miss
Maritime

Essential Advice from The Swedish Club for Masters Handling Liquid Cargo

April 23, 2025

[By: The Swedish Club] The Swedish Club Releases Comprehensive Guide for Proper Sampling Procedures for…

Israel Tells Citizens to Evacuate Houthi-Controlled Ports in Yemen

June 10, 2025

EverLoNG: There are no showstopping regulation to prevent onboard CCS adoption today

March 31, 2025

Montenegro Secures 350M Euros To Enhance Regional

July 24, 2025

Subscribe to Updates

Your Weekly Dive into Maritime & Energy News.

About Us
About Us

Stay informed with the latest in maritime, offshore, oil & gas, and energy industries. Explore news, trends, and insights shaping the global energy landscape.

For advertising inquiries, contact us at
info@maritime247.com.

Facebook X (Twitter) YouTube LinkedIn
Our Picks

WWI Shipwreck Survey to Help Tackle Threats of Environmental Time Bomb

June 14, 2025

Wood open to $320m bid from Sidara after rejecting $2bn last year

April 15, 2025

Corvus ESS Powers the World’s First Fully Electric Offshore Vessel

February 5, 2025

Subscribe to Updates

Your Weekly Dive into Maritime & Energy News.

© 2025 maritime247.com - All rights reserved.
  • Contact
  • Privacy Policy
  • Terms & Conditions
  • Advertising

Type above and press Enter to search. Press Esc to cancel.