Close Menu
  • Home
  • Maritime
  • Offshore
  • Port
  • Oil & Gas
  • Energy
  • Technology
  • Incidents
  • Environment
  • Events
    • Maritime
    • Offshore
    • Oil & Gas
    • Energy
  • Advertising
  • Contact
Facebook X (Twitter) Instagram LinkedIn
Trending
  • Fugro, SDG Data Alliance Partner to Strengthen Climate Resilience in the Caribbean
  • HD Hyundai, H-Line Shipping to develop AI-powered autonomous ship technology
  • Panama’s Comptroller Asks Court to Void Hutchison’s Terminal Concession
  • New 500 kV submarine cable contract to keep ZTT busy offshore China
  • India commissions 1 MW green hydrogen plant at Kandla Port
  • BP renews EnerMech’s contract for work across Caribbean platforms
  • Nexans, Crowley Wind Services to Build Cable Lay Barge for US Ops
  • How marine service providers are helping shipping meet its sustainability goals
Facebook X (Twitter) Instagram LinkedIn
Maritime247.comMaritime247.com
  • Home
  • Maritime
  • Offshore
  • Port
  • Oil & Gas
  • Energy
  • Tech
  • Incidents
  • Environment
  • Events
    • Maritime
    • Oil & Gas
    • Offshore
    • Energy
  • Advertising
Maritime247.comMaritime247.com
Home»Oil & Gas»Delay-induced clouds over UK’s oil & gas decom realm warn of billions in extra costs and fines
Oil & Gas

Delay-induced clouds over UK’s oil & gas decom realm warn of billions in extra costs and fines

July 10, 2025
Facebook Twitter LinkedIn WhatsApp Reddit Tumblr Email
Share
Facebook Twitter LinkedIn Email

The Urgency of Decommissioning Inactive Wells on the UK Continental Shelf

With the backlog of wells due for decommissioning on the rise, the UK’s regulator, the North Sea Transition Authority (NSTA), has issued a stark warning to operators on the UK Continental Shelf (UKCS), urging them to take steps to decommission permanently inactive wells now to stave off a future scenario where they, alongside taxpayers, will need to face cost hikes and potential sanctions because of the missed decommissioning deadlines.

Within its ‘Decommissioning Cost and Performance Update,’ the NSTA highlighted a backlog of over 500 wells, which missed their decommissioning deadline, warning that the figure could grow considerably unless operators quickly ramp up their activities, with more than 1,000 additional wells expected to be due for decommissioning between 2026 and 2030.

Even though some companies are showing good performance in meeting their regulatory duty to decommission wells that have permanently stopped producing, the UK regulator is adamant that many have delayed this work and fallen behind. As a result, they are likely to face higher costs if they continue to keep the supply chain waiting for work, causing further reductions in rig availability as rig owners seek opportunities overseas.

Aside from an uptick in costs, the operators also risk fines as last year the NSTA opened its first investigations into missed deadlines and more could follow in the future. Determined to drive improvements through regulatory measures and data visibility, Britain’s regulator underlines the urgency of tackling the backlog of wells that are already due for decommissioning to stop rigs leaving the North Sea and prevent billions of pounds of additional costs for operators and taxpayers.

See also  TechnipFMC and Vår Energi chart a way forward for ‘faster’ North Sea oil & gas developments

Pauline Innes, NSTA Director of Supply Chain and Decommissioning, remarked: “The NSTA is pulling every lever at our disposal to encourage operators to decommission more wells more quickly. We are willing to help operators when that is necessary but, equally, we are prepared to get tough on those who continually frustrate and delay.

“The stark reality is that operators are running out of time to get to grips with the backlog as more contractors consider taking their rigs abroad, which damages the supply chain’s ability to meet demand and remain cost competitive. We need operators to rise to the challenge and use the supply chain before they lose it.”

Employing ‘carrot and stick’ approach to tackle decom delays

Since operators are obliged by the law to decommission oil and gas infrastructure, including permanently inactive wells, to protect the marine environment in the long term, seen as crucial to safeguarding the sector’s reputation in the eyes of the public and investors, the NSTA claims to be using a ‘carrot and stick’ approach to address the issue.

With this in mind, the regulator has developed an initial plan to show operators how well decommissioning activities could be sequenced; thus, it expects industry to use this information to set up well decommissioning campaigns involving multiple operators and fields, which have demonstrated their ability to save time and money.

The NSTA emphasized: “Well decommissioning should also provide a stream of predictable work for the supply chain, whose transferable skills and equipment could underpin the UK’s transition to net zero and support energy production. The same rigs will be needed to drill carbon storage wells and development wells on approved oil and gas projects.”

“However, not all operators have been awarding well decommissioning contracts quickly enough or on a sufficient scale, compelling rig owners to look for opportunities overseas in hope of securing longer deals and at higher day rates than in the UK. Wells are decommissioned in stages as different types of vessels and equipment are needed to carry out specific jobs.”

The North Sea Transition Authority reported that operators carried out some form of decommissioning work on 223 wells in 2024, progressing 103 of those to final abandonment status, with more than £1 billion (around $1.36 billion) spent on the activity. The regulator sees this as a sign of some operators’ commitment to cleaning up their legacies.

See also  More gas for Europe as Shell turns on the taps at Norwegian field’s next chapter

As about 300 wells need to be fully decommissioned annually to clear the existing backlog and the 1,000 additional wells, which are due to become inactive by 2030, the NSTA’s report pinpoints higher well plug and abandonment (P&A) cost forecasts as the main driver behind the spike in the overall estimate for UKCS decommissioning, which now stands at £41 billion (about $55.56 billion) in constant 2021 prices.

The British regulator believes that minimizing costs benefits taxpayers by slashing the cost of decommissioning tax reliefs to the Exchequer. With fewer rigs in the UKCS to meet projected demand, the pressure on the market will increase and costs will rise further if deferrals continue and more rigs leave the UK.

Commenting on the regulator’s report, Mike Adams, CEO of Elemental Energies, underlined: “As the decommissioning landscape continues to evolve, a major challenge lies ahead. To meet our commitments, coordinated action across operators, regulators, and the supply chain is essential, ensuring alignment and efficiency at every stage. A crucial part of this effort will be harnessing the skills that have been cultivated in the North Sea over decades.

“These skills are now ideally placed to support the transition of these assets through late life and into decommissioning, especially with the expertise of offshore teams who have operated and maintained these assets for years. It is these teams who will be vital in driving efficiency and ensuring safe, timely, and cost-effective decommissioning.”

The NSTA underscores that these costs have the potential to increase by more than £4 billion (over $5.42 billion), as reactivating rigs or attracting vessels back to the United Kingdom from overseas is bound to be costly and add further delays to the decommissioning schedules.

See also  Norwegian cleantech services firm gets to work on giant Black Sea gas project

Adams added: “Continued investment in the development of new technologies will be essential. Much of this innovation is happening right here in the North East of Scotland, and these advancements will make a material difference in reducing time and cost across the P&A process, enhancing the overall efficiency of the sector.”

Billions Clouds Costs decom Delayinduced extra Fines gas Oil realm UKs Warn
Share. Facebook Twitter LinkedIn Tumblr Telegram Email

Related Posts

BP renews EnerMech’s contract for work across Caribbean platforms

July 31, 2025

Long-term LNG deal with Canadian player diversifying Uniper’s portfolio

July 31, 2025

Baker Hughes’ $13.6 billion move on Chart spotlights gas, data centers, and decarbonization growth drivers

July 31, 2025
Top Posts

Duties of Bosun (Boatswain) on a Ship

February 1, 2025

China Fights Australia’s Plans to Reclaim Darwin Port Citing U.S. Influence

May 27, 2025

Fire-Stricken Wan Hai 503 Continues to Drift Off Indian Coast as Salvage Efforts Intensify

June 11, 2025

Car Carrier ‘Morning Midas’ Catches Fire with Electric Vehicles Off Alaska

June 5, 2025
Don't Miss
Maritime

World’s second-largest owner opens Washington office

April 25, 2025

MOL In a sign of the times, Japan’s Mitsui OSK Lines (MOL), the world’s second-largest…

Subsea Warfare Need Not Involve Target Destruction

June 20, 2025

WinGD calls for ‘strong’ measures to meet maritime GHG targets

February 25, 2025

What Will Happen If Iran Closes The Strait of Hormuz?

June 25, 2025

Subscribe to Updates

Your Weekly Dive into Maritime & Energy News.

About Us
About Us

Stay informed with the latest in maritime, offshore, oil & gas, and energy industries. Explore news, trends, and insights shaping the global energy landscape.

For advertising inquiries, contact us at
info@maritime247.com.

Facebook X (Twitter) YouTube LinkedIn
Our Picks

China’s first domestic ammonia bunkering operation completed

January 4, 2025

SMD and Beam Go Deeper for AI-Driven Autonomous Offshore Wind Inspections

January 13, 2025

Coastal Marine Ecosystems May Need Active Restoration

June 23, 2025

Subscribe to Updates

Your Weekly Dive into Maritime & Energy News.

© 2025 maritime247.com - All rights reserved.
  • Contact
  • Privacy Policy
  • Terms & Conditions
  • Advertising

Type above and press Enter to search. Press Esc to cancel.